MLI Cutover Major Milestones & Activities

 

Task Day Time (Eastern) Time (Pacific) Status
Begin Cutover Staffing Plan (War room Open) Friday      
Intellinet Environment - Daily Processing Completed Friday 9:15 PM 6:15 PM  
Intellinet Environment Disabled - Begin to bring up RISC / SISC Saturday 6:05 AM 3:05 AM  
RISC / SISC Active - ET Testing Completed Saturday 11:10 AM 8:10 AM  
Begin AD / QA / Partner Testing Saturday 12:30 PM 9:30 AM  

Foresight - All Testing Completed

Saturday 4:15 PM 1:15 PM  

Irvine - All Testing Completed

Saturday 5:45 PM 2:45 PM  

LA & WDM - All Testing Completed

Saturday 7:00 PM 4:00 PM  

Declare Success

Saturday 7:30 PM 4:30 PM  

Week One Staffing Schedule To Begin

Saturday 8:00 PM 5:00 PM  

 

 